Currently, Lower Towamensing Township has one projects that is underway:


 


Township Sewer Service Collection:

In 2017, the Department of Environmental Protection  approved the planning documents for the Township's Sewer Treatment System, The area for sewer service being proposed is the villages of Aquashicola and Little Gap, and covers the Weiner's Trailer Park portion of the township. Additionally, the service area extends north to the former "Fernbrook" property of Forest Inn Road, and West up Fireline Road to the Palmerton Area High School. The main section of the line will run along Little Gap Road to the Blue Mountain Ski Area Sewer Treatment Plant.

FUTURE PLANS:

 

December 2020 ~ Township shall adopt On-Lot Sewage Management Program Ordinance

December 2020 ~ Obtain PNDI search impact resolutions from appropriate agencies

February 2021 ~ Township shall adopt updated Holding Tank Ordinance

March 2021 ~ Complete design of Lower Towamensing Sewage System (including Construction Plans, HOPs, ESPC Plans, ESPC Narrative, Post Construction Stormwater Management (PCSM) Plans), PCSM Narrative, Pumping Station Design Calculations, Wetlands Encroachment Plans, Stream Crossing Plans)

April 2021 ~ Submit NPDES Permit Application to Carbon County Conservation District (CCCD) and PA DEP (this includes overall ESPC Plans and PCSM Plans)

April 2021 ~ Submit stream crossing permit applications (General Permits, GPs) to the PA DEP

April 2021 ~ Submit GP or Joint Permit Application for wetlands encroachment to the PA DEP

April 2021 ~ Submit permit applications for pumping stations (Part II Water Quality Permit) to the PA DEP

July 2021 ~ Obtain all necessary easements

September 2021 ~ Obtain HOP Permit, NPDES Permit, Stream Crossing Permits, Wetlands Encroachment Permit, and Pumping Station Permits

October 2021 ~ Prepare Contract

November 2021 ~ Submit application/design report to USDA Rural Development Agency for funding

            

December 2021 ~ Obtain USDA funding approval

February 2022 ~ Submit construction bidding documents, final plans, and specifications to the PA DEP

March 2022 ~ Obtain approval of construction bidding documents, final plans, and specifications from the PA DEP

April 2022 ~ Advertised for Bids

May 2022 ~ Township shall receive bids

June 2022 ~ Township shall award contract and provide Notice to Proceed to Contractor

August 2022 ~ Hold pre-construction meeting

September 2022 ~ Begin construction

November 2022 ~ Township shall adopt Mandatory Sewer Connection Ordinance

January 2023 ~ Township shall adopt Ordinance setting forth computational methods of sewer rentals or charges, and setting fees for connections to the sewer system, and setting the types of materials to be used for building sewers

November 2023 ~ Complete construction

December 2023 ~ Begin connection of building sewers to laterals

      

December 2024 ~ Complete connection of building sewers to laterals

April 2025 ~ Begin final pavement restoration

November 2025 ~ Complete final pavement restoration

March 2026 ~ Perform As-Built Survey of all completed work

July 2026 ~ Submit As-Built Plan and NPDES Permit Notice of Termination to CCCD and PA DEP

January 2027 ~ Begin Evaluation and Update of Act 537 Plan as necessary